need this answered, will give thhmbs up Question 22 1 pts Product A has an on-hand (OH) of 100, lead time (LT) of 1 week,
need this answered, will give thhmbs up
Question 22 1 pts Product A has an on-hand (OH) of 100, lead time (LT) of 1 week, safety stock (SS) of O and lot size (0) of 200. Using the additional information below for product A, what would be the planned order release for week 2? 1 2 3 450 Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipt Planned order release 100 100 350 00 O 200 O 350 O 400 Step by Step Solution