New Education Corporation is a rapidly growing biotech company that has a requiled rate of return of 6%. It plans to build a new facility in Santa Clara County. The building will take 2 years to complete. The building contractor offered New Education a choice of three payment plans, as follows: (Click the icon to view the data) Present Value of $1 table Read the requirements. Requirement 1. Using the net present value method, calculate the comparative cost of each of the three payment plans being considered by New Education. (Round your final answers to the nearest whole dollar.) The net present value cost of Plan I is Mctee info - Plan I: Payment of $225,000 at the time of signing the contract and $4,725,000 upon completion of the building. The end of the second year is the completion date. - Plan II: Payment of $1,800,000 at the time of signing the contract and $1,800,000 at the end of each of the two succeeding years. - Plan III: Payment of $325,000 at the time of signing the contract and $1,625,000 at the end of each of the three succeeding years. Requirements 1. Using the net present value method, calculate the comparative cost of each of the three payment plans being considered by New Education. 2. Which payment plan should New Education choose? Explain. 3. Discuss the financial factors, other than the cost of the plan, and the nonfinancial factors that should be considered in selecting an appropriate payment plan. New Education Corporation is a rapidly growing biotech company that has a required rate of return of 6%. It plans to build a new facility in Santa Clara County. The buliding will take 2 years to complete. The building contractor offered New Education a choice of three payment plans. as follows: (Click the icon to view the data) Future Value of Annuity of 51 table Present Value of $1 table Read the requirements. Requirement 1. Using the net present value method, calculate the comparative cost of each of the three payment plans being considered by New Education. (Round your final answers to the nearest whole dollar.) The net present value cost of Plan 1 is More info - Plan I: Payment of $225,000 at the time of signing the contract and $4,725,000 upon completion of the building. The end of the second year is the completion date. - Plan II: Payment of $1,800,000 at the time of signing the contract and $1,800,000 at the end of each of the two succeeding years. - Plan III: Payment of $325,000 at the time of signing the contract and $1,625,000 at the end of each of the three succeeding years. Requirements 1. Using the net present value method, calculate the comparative cost of each of the three payment plans being considered by New Education. 2. Which payment plan should New Education choose? Explain. 3. Discuss the financial factors, other than the cost of the plan, and the nonfinancial factors that should be considered in selecting an appropriate payment plan. Reference Reference Reference Reference Reference Reference Reference New Education Corporation is a rapidly growing biotech company that has a requiled rate of return of 6%. It plans to build a new facility in Santa Clara County. The building will take 2 years to complete. The building contractor offered New Education a choice of three payment plans, as follows: (Click the icon to view the data) Present Value of $1 table Read the requirements. Requirement 1. Using the net present value method, calculate the comparative cost of each of the three payment plans being considered by New Education. (Round your final answers to the nearest whole dollar.) The net present value cost of Plan I is Mctee info - Plan I: Payment of $225,000 at the time of signing the contract and $4,725,000 upon completion of the building. The end of the second year is the completion date. - Plan II: Payment of $1,800,000 at the time of signing the contract and $1,800,000 at the end of each of the two succeeding years. - Plan III: Payment of $325,000 at the time of signing the contract and $1,625,000 at the end of each of the three succeeding years. Requirements 1. Using the net present value method, calculate the comparative cost of each of the three payment plans being considered by New Education. 2. Which payment plan should New Education choose? Explain. 3. Discuss the financial factors, other than the cost of the plan, and the nonfinancial factors that should be considered in selecting an appropriate payment plan. New Education Corporation is a rapidly growing biotech company that has a required rate of return of 6%. It plans to build a new facility in Santa Clara County. The buliding will take 2 years to complete. The building contractor offered New Education a choice of three payment plans. as follows: (Click the icon to view the data) Future Value of Annuity of 51 table Present Value of $1 table Read the requirements. Requirement 1. Using the net present value method, calculate the comparative cost of each of the three payment plans being considered by New Education. (Round your final answers to the nearest whole dollar.) The net present value cost of Plan 1 is More info - Plan I: Payment of $225,000 at the time of signing the contract and $4,725,000 upon completion of the building. The end of the second year is the completion date. - Plan II: Payment of $1,800,000 at the time of signing the contract and $1,800,000 at the end of each of the two succeeding years. - Plan III: Payment of $325,000 at the time of signing the contract and $1,625,000 at the end of each of the three succeeding years. Requirements 1. Using the net present value method, calculate the comparative cost of each of the three payment plans being considered by New Education. 2. Which payment plan should New Education choose? Explain. 3. Discuss the financial factors, other than the cost of the plan, and the nonfinancial factors that should be considered in selecting an appropriate payment plan. Reference Reference Reference Reference Reference Reference Reference