Question
Next, you have a meeting with a project manager to review the sensitivity of projects and risk analysis tools. You are reviewing the following results
Next, you have a meeting with a project manager to review the sensitivity of projects and risk analysis tools.
You are reviewing the following results from a projects sensitivity analysis. The project manager wants your opinion on which value drivers should be the firms focus for this project. Which value driver should be the focus?
Value Drivers | Baseline NPV | Sensitivity Analysis NPV | % Change |
Unit Sales (-10%) | $273,000 | $250,000 | -8.42% |
Price per unit (-10%) | $273,000 | -$25,000 | -109.16% |
Variable cost (+10%) | $273,000 | $175,000 | -35.90% |
Cash fixed cost (+10%) | $273,000 | $263,000 | -3.66% |
Which is the best response regarding where the firm should focus their attention first?
A. Management should focus on fixed costs
B. Management should focus on price per unit
C. Management should focus on variable costs
D. Management should focus solely on NPV and IRR of the baseline analysis
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started