Next you review data for a replacement project to upgrade robots to ESG standards. The preliminary budget is below. Put an X next to the
Next you review data for a replacement project to upgrade robots to ESG standards. The preliminary budget is below. Put an X next to the budget items that would NOT be included in project cash flows.
Budget:
Market Research $25,000
Decrease in annual electricity $35,000
Lost revenue in robot downtime $125,000
Increase in working capital $55,000
Continued robot maintenance cost $10,000
Increased revenue from robots $200,00