Question

1 Approved Answer

Nova Companys total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 46,000 $ 180,540 May 36,000

Nova Companys total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost

April 46,000 $ 180,540 May 36,000 $ 156,640 June 56,000 $ 204,440 July 66,000 $ 228,340

Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 36,000 machine-hour level of activity is:

Utilities (variable) $ 43,200 Supervisory salaries (fixed) 58,000 Maintenance (mixed) 55,440 Total overhead cost $ 156,640 Nova Companys management wants to break down the maintenance cost into its variable and fixed cost elements. Required: 1. Estimate how much of the $228,340 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first determine how much of the $228,340 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.) 2. Using the high-low method, estimate a cost formula for maintenance in the form Y = a + bX. 3. Express the companys total overhead cost in the form Y = a + bX. 4. What total overhead cost would you expect to be incurred at an activity level of 41,000 machine-hours?

A. Estimate how much of the $228,340 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first determine how much of the $228,340 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.) (Do not round intermediate calculations.)

B. Using the high-low method, estimate a cost formula for maintenance in the form Y = a + bX. (Do not round your intermediate calculations. Round the "Variable cost per unit" to 2 decimal places.)

C.

Express the companys total overhead cost in the form Y = a + bX. (Do not round your intermediate calculations. Round the "Variable cost per unit" to 2 decimal places.)

Variable Cost per
Machine-Hour Fixed Cost
Utilities cost
Supervisory salaries cost
Maintenance cost
Total overhead cost

Y= _______ + ________ X

D. What total overhead cost would you expect to be incurred at an activity level of 41,000 machine-hours?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Internationale Rechnungslegung IFRS Praxis

Authors: Author

1st Edition

3834909289, 9783834909282

More Books

Students also viewed these Accounting questions

Question

Express the given angles to the nearest minute. 749.75

Answered: 1 week ago