Question
Nova Construction Company (NCC) entered into a contract to build a school for $1,800,000. Construction commenced on May 1, 2020, with a planned completion date
Nova Construction Company (NCC) entered into a contract to build a school for
$1,800,000.
Construction commenced on May 1, 2020, with a planned completion date of December 31, 2022. A summary of the related accounting information is provided below:
2020 | 2021 | 2022 | |
---|---|---|---|
Costs incurred during the year | $400,000 | $500,000 | $650,000 |
Estimated costs to complete at year-end | 1,200,000 | 600,000 | 0 |
Billings during the year | 560,000 | 640,000 | 600,000 |
Cash collections during the year | 500,000 | 310,000 | 990,000 |
How much gross profit would be recognized in fiscal 2020 if NCC uses the percentage of completion method?
A. $130,000
B. $100,000
C. $180,000
D. 50000
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started