ob Order Cost Sheet Stretch and Trim Carpet Company sells and installs commercial carpeting for office buildings. Stretch and Trim Carpet Company uses a job

ob Order Cost Sheet

Stretch and Trim Carpet Company sells and installs commercial carpeting for office buildings. Stretch and Trim Carpet Company uses a job order cost system. When a prospective customer asks for a price quote on a job, the estimated cost data are inserted on an unnumbered job cost sheet. If the offer is accepted, a number is assigned to the job, and the costs incurred are recorded in the usual manner on the job cost sheet. After the job is completed, reasons for the variances between the estimated and actual costs are noted on the sheet. The data are then available to management in evaluating the efficiency of operations and in preparing quotes on future jobs. On May 9, Stretch and Trim gave Lunden Consulting an estimate of $18,044 to carpet the consulting firms newly leased office. The estimate was based on the following data:

Estimated direct materials:
400 meters at $32 per meter $12,800
Estimated direct labor:
30 hours at $20 per hour 600
Estimated factory overhead (80% of direct labor cost) 480
Total estimated costs $13,880
Markup (30% of production costs) 4,164
Total estimate $18,044

On May 10, Lunden Consulting signed a purchase contract, and the carpet was delivered and installed on May 15.

The related materials requisitions and time tickets are summarized as follows:

Materials Requisition No. Description Amount
132 360 meters at $32 $11,520
134 50 meters at $32 1,600
Time Ticket No. Description Amount
H9 18 hours at $19 $342
H12 18 hours at $19 342

Required:

Enter amounts as positive numbers. Round answers to the nearest whole dollar.

1. Complete that portion of the job order cost sheet that would be prepared when the estimate is given to the customer.

2. Record the costs incurred, and complete the job order cost sheet.

JOB ORDER COST SHEET
Customer Lunden Consulting Date May 9
Date wanted May 15
Date completed May 15
Job. No.
ESTIMATE
Direct Materials Direct Labor Summary
Amount Amount Amount
400 meters at $32 fill in the blank ba3296062025061_1 30 hours at $20 fill in the blank ba3296062025061_2 Direct Materials fill in the blank ba3296062025061_3
Direct Labor fill in the blank ba3296062025061_4
Factory Overhead fill in the blank ba3296062025061_5
Total fill in the blank ba3296062025061_6 Total fill in the blank ba3296062025061_7 Total cost fill in the blank ba3296062025061_8
ACTUAL
Direct Materials Direct Labor Summary
Mat. Req. No. Description Amount Time Ticket No. Description Amount Item Amount
132 360 meters at $32 fill in the blank ba3296062025061_9 H9 18 hours at $19 fill in the blank ba3296062025061_10 Direct Materials fill in the blank ba3296062025061_11
Direct Labor fill in the blank ba3296062025061_12
134 50 meters at $32 fill in the blank ba3296062025061_13 H12 18 hours at $19 fill in the blank ba3296062025061_14 Factory Overhead fill in the blank ba3296062025061_15
Total fill in the blank ba3296062025061_16 Total fill in the blank ba3296062025061_17 Total Cost fill in the blank ba3296062025061_18

Feedback

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accountability Ethics And Sustainability Of Organizations

Authors: Sandro Brunelli, Emiliano Di Carlo

3rd Edition

3030311929, 9783030311926

More Books

Students also viewed these Accounting questions