Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Ollivier Corporation has an activity-based costing system with three activity cost pools-Processing, Supervising, and Other. In the first stage allocations, costs In the two overhead
Ollivier Corporation has an activity-based costing system with three activity cost pools-Processing, Supervising, and Other. In the first stage allocations, costs In the two overhead accounts, equipment expense and Indirect labor, are allocated to the three activity cost pools based on resource consumption. Data used In the first stage allocatlons follow Overhead costs Equipment expense Indirect labor $98,000 $7,900 Distribution of Resource Consumption Across Activity Cost Pools Activity Cost Pools Processing SupervisngOther Equipment expense Indirect labor 0.20 0.20 0.60 0.50 0.20 0.30 Processing costs are assigned to products using machine-hours (MHs) and Supervising costs are assigned to products using the number of batches. The costs In the Other activity cost pool are not assigned to products Activity data for the company's two products follow Activity MHs (Processing)Batches (Supervising) Product C4 Product L7 Total 18,700 2,070 20,770 710 1,340 2,050 What is the overhead cost assigned to Product L7 under activity-based costing? (Round your intermediate calculations to 2 decimal places and final answer to the nearest dollar amount.) O $43,129 O $2.111 $41,017 O $53107
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started