Question
OM Construction Company must choose between two types of cranes. Crane A costs $600,000, will last for five years, and will require $60,000 in maintenance
OM Construction Company must choose between two types of cranes. Crane A costs $600,000, will last for five years, and will require $60,000 in maintenance each year. Crane B costs $750,000, will last for seven years, and will require $30,000 in maintenance each year. Maintenance costs for cranes A and B occur at the end of each year. The appropriate discount rate is 12% per year. Which machine should OM Construction purchase?
Crane A as EAC is $226,444 | ||
Crane B as EAC is $194,336 | ||
Crane A because its PV is $816,286, i.e., less than the PV of Project B | ||
Cannot be calculated as the revenues for the project are not given |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started