On 1 January 2017, Sun & Moon Bhd constructed a building in Parit Jawa.The estimated cost of construction was RM5,000,000 and it was scheduled to

On 1 January 2017, Sun & Moon Bhd constructed a building in Parit Jawa.The estimated cost of construction was RM5,000,000 and it was scheduled to be completed on 30 June 2019. In order to finance the construction, Sun & Moon Bhd took a 5-year term loan of RM4,000,000 at an effective interest rate of 7% per annum on 1 July 2016.Sun & Moon Bhd invested RM1,000,000 of the loan in a 12-month fixed deposit from 1 July 2016 till 30 June 2017 earning a return of 3% per annum.The construction was interrupted for few months from 1 February 2018 to 30 April 2018 due to insufficient of raw materials to continue the project. The construction was finally completed as scheduled. The newly constructed building was used on 1 July 2019 and has an expected useful life of 50 years. The asset is depreciated based on yearly basis.

On 31 December 2019, the fair value less cost to sell of this building was RM3,500,000 and its projected cash flows are as follows:

Year ended

RM

31/12/2019

1,300,000

31/12/2020

1,200,000

31/12/2021

2,100,000

The company's incremental borrowing rate was 10%. The present value table for single sums, wherei= interest andn= years is given below:

n

i

1

0.909

2

0.826

3

0.751

1.Calculate the initial costs of the building in Parit Jawa.

a)RM5,810,000

b)RM5,615,000

c)RM5,740,000

d)RM5,630,000

ANSWER:

2.Sun & Moon Bhd incurred further expenditure on the head office extension after it has been completed on 1 July 2019. Which one of the following will qualify as capital expenditure?

a)Property insurance premium incurred

b)Installation of new office fixtures and fittings

c)Marketing costs telling the public that the extension is operational

d)Relocation of office equipment

ANSWER:

3.Find the true statement in relation to income from the temporary investment of the borrowing.

i.Income earned on such investments will reduce the amount of borrowing costs that can be capitalised during the commencement period and before the completion period.

ii.During the suspension period, any income earned on such investments will be credited to profit or loss account.

iii.During the suspension period, any income earned on such investments will be credited to retained earnings.

a)None of the above

b)i

c)i and ii

d)i, ii and iii

ANSWER:

4.Which of the following circumstances may indicate that the building may have become impaired?

a)Significant changes in global oil price

b)Labour strike that affect the constructions of the building

c)Significant damage of the building that affect the usage of the building

d)Covid-19 pandemic

ANSWER;

5.Determine the net recoverable amount of the building.

a)RM3,500,000

b)RM3,750,000

c)RM5,573,700

d)RM5,517,400

ANSWER;

6.Calculate the impairment loss of the building.

a)RM2,002,700

b)RM1,752,700

c)RM1,823,700

d)RM1,808,850

ANSWER:

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Audit Sampling

Authors: Ray Whittington, Dan M Guy, D R Carmichael

5th Edition

047137590X, 9780471375906

More Books

Students also viewed these Accounting questions

Question

Would I be a more effective student if I spent less time online?

Answered: 1 week ago