On April 1 , 2 0 2 5 , Ivanhoe Inc. entered into a cost plus fixed fee contract to construct an electric generator for

On April 1,2025, Ivanhoe Inc. entered into a cost plus fixed fee contract to construct an electric generator for Metlock Corporation. At the contract date, Ivanhoe estimated that it would take 2 years to complete the project at a cost of $2,200,000. The fixed fee stipulated in the contract is $443,000. Ivanhoe appropriately accounts for this contract under the percentage-of-completion method. During 2025, Ivanhoe incurred costs of $946,000 related to the project. The estimated cost at December 31,2025, to complete the contract is $1,254,000. Metlock was billed $555,000 under the contract.
Prepare a schedule to compute the amount of gross profit to be recognized by Ivanhoe under the contract for the year ended December 31,2025.(If an amount reduces the account balance then enter with negative sign., e.g.-45 or parentheses e.g.(45).)
IVANHOE INC.
Computation of Gross Profit to be Recognized on Uncompleted Contract
$
%
$
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Comparative international accounting

Authors: Christopher nobes, Robert parker

9th Edition

273703579, 978-0273703570

More Books

Students also viewed these Accounting questions