On April 1, 2017, Bridgeport Inc. entered into a cost plus fixed fee contract to construct an electric generator for Altom Corporation. At the contract

On April 1, 2017, Bridgeport Inc. entered into a cost plus fixed fee contract to construct an electric generator for Altom Corporation. At the contract date, Bridgeport estimated that it would take 2 years to complete the project at a cost of $2,010,000. The fixed fee stipulated in the contract is $470,000. Bridgeport appropriately accounts for this contract under the percentage-of-completion method. During 2017, Bridgeport incurred costs of $824,100 related to the project. The estimated cost at December 31, 2017, to complete the contract is $1,185,900. Altom was billed $610,000 under the contract. Prepare a schedule to compute the amount of gross profit to be recognized by Bridgeport under the contract for the year ended December 31, 2017. Show supporting computations in good form.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Intermediate Accounting Volume 2

Authors: Thomas Beechy, Joan Conrod, Elizabeth Farrell, Ingrid McLeod-Dick

7th Edition

1259108023, 9781259108020

More Books

Students also viewed these Accounting questions