Question
On April 1, 2019, Aria Constructions Co. contracted to build an office building for Mulla Co. for a total contract price of $4,560,000. The building
On April 1, 2019, Aria Constructions Co. contracted to build an office building for Mulla Co. for a total contract price of $4,560,000. The building was substantially completed on December 31, 2021. Following are data related to the construction:
Dec 31, 2019 | Dec 31, 2020 | Dec 31, 2021 | |
---|---|---|---|
Contract costs incurred to date | 720,000 | 2,880,000 | 5,040,000 |
Estimated costs to complete | 2,880,000 | 1,920,000 | 0 |
Billings to Mulla | 720,000 | 2,640,000 | 1,200,000 |
Required:
a. Using the percentage of completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2019, 2020, 2021 and please explain the results!
b. Using the cost recovery method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2019, 2020, 2021 and please explain the results
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started