On December 31, 2019, Mass Construction Inc. signs a contract with the state of Massachusetts Department of Transportation to manufacture a bridge over the Merrimack.

On December 31, 2019, Mass Construction Inc. signs a contract with the state of Massachusetts Department of Transportation to manufacture a bridge over the Merrimack. Mass Construction anticipates the construction will take three years. The company's accountants provide the following contract details relating to the project:

Contract price

$520 million

Estimated construction costs

$300 million

Estimated total profit

$220 million

During the three-year construction period, Tri-State incurred costs as follows:

2020

$ 60 million

2021

$150 million

2022

$ 90 million

Tri-State uses the percentage of completion method to recognize revenue. Which of the following represent the profits recognized in 2020, 2021, and 2022?

A.

$44 million, $110 million, $66 million

B.

$52 million, $312 million, $156 million

C.

None of the above

D.

$104 million, $260 million, $156 million

E.

$104 million, $110 million, $66 million

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The FinTech Book The Financial Technology Handbook For Investors Entrepreneurs And Visionaries

Authors: Susanne Chishti, Janos Barberis

1st Edition

111921887X, 9781119218876

More Books

Students also viewed these Finance questions