On December 31, 20x5, you enter into a three year contract to build an office building for $18136139. At the end of 20x6, you incurred
On December 31, 20x5, you enter into a three year contract to build an office building for $18136139. At the end of 20x6, you incurred $4182186 of costs and expect to incur an additional $6036556 to complete the contract. How much profit will you realize on this contract in 20x6?
Select one:
a. 7917397
b. 2639132
c. 3240323
d. 4677074