On February 1, 2017, Marsh Contractors agreed to construct a building at a contract price of $17,400. Marsh estimated total construction costs would be $12,000

On February 1, 2017, Marsh Contractors agreed to construct a building at a contract price of $17,400. Marsh estimated total construction costs would be $12,000 and the project would be finished in 2019. Information relating to the costs and billings for this contract is as follows:

2017 2018 2019
Total costs incurred to date $4,500 $7,920 $13,800
Estimated costs to complete 7,500 5,280 -0-
Customer billings to date 6,600 12,000 16,800
Collections to date 6,000 10,500 16,500

Record the 2018 journal entry for cash collections.

Dr. Cash Blank 1

Cr. Accounts Recievable

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Accounting questions

Question

8. Explain the contact hypothesis.

Answered: 1 week ago

Question

7. Identify four antecedents that influence intercultural contact.

Answered: 1 week ago