Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

On February 1, 2020, Blossom Contractors agreed to construct a building at a contract price of $3,430,000. The total estimated construction costs would be

image text in transcribed

On February 1, 2020, Blossom Contractors agreed to construct a building at a contract price of $3,430,000. The total estimated construction costs would be $2,005,000 and the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows: 2020 2021 2022 Total costs incurred to date $ 721,800 $ 1,090,000 $ 2,250,000 Estimated costs to complete 1,283,200 1,090,000 -0- Customer billings to date 1,100,000 2.005,000 3,430,000 Collections to date 1,000,000 1,750,000 2,950,000 Calculate the gross profit/(loss) that should be recognized for 2020, 2021, and 2022 using the percentage completion method. (Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).) Gross profit/(loss) $ 2020 $ 2021 $ 2022

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Government and Not for Profit Accounting Concepts and Practices

Authors: Michael H. Granof, Saleha B. Khumawala

6th edition

978-1-119-4958, 9781118473047, 1118155971, 1118473043, 978-1118155974

More Books

Students also viewed these Accounting questions

Question

Prepare a bank reconciliation. AppendixLO1

Answered: 1 week ago

Question

How can they use Your Personal Financial Plan sheets 2630?

Answered: 1 week ago