Question

1 Approved Answer

On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,425,000. During 2021, costs

image text in transcribedimage text in transcribedimage text in transcribedimage text in transcribed

On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,425,000. During 2021, costs of $2,170,000 were incurred, with estimated costs of $4,170,000 yet to be incurred. Billings of $2,704,000 were sent, and cash collected was $2,420,000. In 2022, costs incurred were $2,704,000 with remaining costs Zestimated to be $3,855,000.2022 billings were $2,954,000, and $2,645,000 cash was collected. The project was completed in 2023 after additional costs of $3,970,000 were incurred. The company's fiscal year-end is December 31. This project does not qualify for revenue recognition over time. Required: 1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years. 2a. Prepare journal entries for 2021 to record the transactions described (credit "various accounts" for construction costs incurred). 2b. Prepare journal entries for 2022 to record the transactions described (credit "various accounts" for construction costs incurred). 3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2021. 3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2022. Reg 1 Req 2A Reg 2B Req Req 3B Prepare journal entries for 2022 to record the transactions described (credit "various accounts" for construction costs incurred). (If no entry is required for a transaction/event, select "No journal entry required" in the first account field.) No Year General Journal Debit Credit 1 2022 Construction in progress 2,704,000 Various accounts 2,704,000 2 2022 Accounts receivable 2,954,000 Billings on construction contract 2,954,000 3 2022 Cash 2,645,000 Accounts receivable 2,645,000 4 2022 Construction in progress Req 1 Req 2A Req 2B Req Req 3B Prepare a partial balance sheet to show the presentation of the project as of December 31, 2021. (Do not round intermediate calculations. Round your answers to the nearest dollar amount.) Balance Sheet At December 31, 2021 Current assets: Accounts receivable Billings in excess of costs Current liabilities: Billings in excess of costs less loss

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting Best Practices

Authors: Steven M. Bragg

3rd Edition

0471444286, 978-0471444282

More Books

Students also viewed these Accounting questions

Question

What do you see as your biggest strength/weakness?

Answered: 1 week ago