On February 1, 2024, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2024,

image text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribed

On February 1, 2024, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2024, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2025, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2025 billings were $2,850,000, and $2,575,000 cash was collected. The project was completed in 2026 after additional costs of $3,900,000 were incurred. The company's fiscal year-end is December 31. Arrow recognizes revenue over time according to percentage of completion. Required: 1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years. 2a. Prepare journal entries for 2024 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred). 2b. Prepare journal entries for 2025 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred). 3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2024. 3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2025. Complete this question by entering your answers in the tabs below. Req 1 Req 2A Req 2B Req 3A Req 3B Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years. Note: Do not round intermediate calculations. Loss amounts should be indicated with a minus sign. Round your final answers to the nearest whole dollar. 2024 2025 2026 Percentages of completion = 2024 To date Recognized in prior years Recognized in 2024 Construction revenue Construction expense Gross profit (loss) $ 0 $ 0 $ 0 Construction revenue Construction expense Gross profit (loss) Construction revenue Construction expense Gross profit (loss) 2025 To date Recognized in prior years Recognized in 2025 $ $ $ 2026 To date Recognized in prior years Recognized in 2026 $ $ $ < Req 1 Req 2A > 0

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to Accounting An Integrated Approach

Authors: Penne Ainsworth, Dan Deines

6th edition

78136601, 978-0078136603

More Books

Students also viewed these Accounting questions

Question

What is meant by the term equal service?

Answered: 1 week ago

Question

Understand the importance of public insurance programs

Answered: 1 week ago

Question

=+b) Should the company send the fact-finding trip? Explain.

Answered: 1 week ago

Question

Prove that if Σ an is absolutely convergent, then a. an

Answered: 1 week ago