Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

On January 1, 2016, the controller of Omicron Inc. is planning capital expenditures for the years 2016-2019. The following interviews helped the controller collect the

image text in transcribed

On January 1, 2016, the controller of Omicron Inc. is planning capital expenditures for the years 2016-2019. The following interviews helped the controller collect the necessary information for the capital expenditures budget Director of Facilities: A construction contract was signed in late 2015 for the construction of a new factory building at a contract cost of $10,000,000. The construction is scheduled to begin in 2016 and be completed in 2017 Vice President of Manufacturing: Once the new factory building is finished, we plan to purchase $1.5 million in equipment in late 2017. I expect that an additional $200,000 will be needed early in the following year (2018) to test and install the equipment before we can begin production. If sales continue to grow, I expect we'll need to invest another $1,000,000 in equipment in 2019 Chief Operating Officer. We have eally been growing lately. I wouldn't be surprised if we need to expand the size of our new factory building 20 y atleast 3 % Fortunately, we expect inflation to have minimal impact on construction costs over the next four years. Additionally, I would expect the cost of the expansion to be proportional to the size of the expansion Director of Information Systems: We need to upgrade our information systems to wireless network technology. It doesn't make sense to do this until after the new factory building is completed and producing product. During 2018, once the factory is up and running, we should equip the whole facility with wireless technology. I think it would cost us $800,000 today to install the technology. However, prices have been dropping by 25% per year, so it should be less expensive at a later date Chief Financial Officer: I am excited about our long-term prospects. My only short-term concern is managing our cash flow while we expend the $4,000,000 of construction costs on the portion of the new factory building scheduled to be completed in 2016 Omicron Inc. Capital Expenditures Budget For the Four Years Ending December 31, 2016-2019 201620172018 2019 term concern is managing our cash flow while w Building Equipment Information systems Total

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Value Based Management Context And Application

Authors: Glen Arnold, Matt Davies

1st Edition

0471899860, 978-0471899860

More Books

Students also viewed these Accounting questions

Question

=+ Did your need for control change as the venture grew?

Answered: 1 week ago

Question

=+Explain the skills needed to create a sustainable personal bran

Answered: 1 week ago