Question
On January 1, 2019, Bryan Construction entered into a three-year contract to build a new highway in Manitoba for a total contract price of $15,000,000.
On January 1, 2019, Bryan Construction entered into a three-year contract to build a new highway in Manitoba for a total contract price of $15,000,000. The cost of the project is estimated at $12,000,000. The company uses the percentage of completion method and its year-end is December 31st, 2020.
Year | 2019 | 2020 |
Costs incurred to date on the project (cumulative) | $4,200,000 | $9,000,000 |
Estimated remaining costs to complete, as at end of year | 7,800,000 | 3,000,000 |
Required:
a) (2 marks) Compute the dollar amount of the revenue recognized at the end of 2019.
b) (2 marks) Write the journal entry to record the 2020 construction costs.
c) (2 marks) Write the entry to record progress billings of $4,000,000 for 2020.
d) (4 marks) Write the entry or entries to recognize the revenue and profit to be recognized in the 2020 year
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started