Question
On January 1, 2020, Miller Construction Company contracted to build a parking lot for the city of St. Louis for $675,000. The following transactions and
On January 1, 2020, Miller Construction Company contracted to build a parking lot for the city of St. Louis for $675,000. The following transactions and estimates relate to this contract.
Construction costs incurred during 2020 | $360,000 |
Progress billings | $171,000 |
Cash collections | $157,500 |
Estimated costs to complete | $360,000 |
a. Prepare the 2020 journal entry to record profit or loss assuming revenue is recognized over time. Note: Record any multiple debits in alphabetical order and any multiple credits in alphabetical order.
Account | Debit | Credit | |
---|---|---|---|
a. | AnswerCashAccounts ReceivableConstruction in ProcessBillings on ContractsLoss from Long Term ContractsRevenue from Long Term ContractsCost of ConstructionN/A | Answer | Answer |
AnswerCashAccounts ReceivableConstruction in ProcessBillings on ContractsLoss from Long Term ContractsRevenue from Long Term ContractsCost of ConstructionN/A | Answer | Answer | |
AnswerCashAccounts ReceivableConstruction in ProcessBillings on ContractsLoss from Long Term ContractsRevenue from Long Term ContractsCost of ConstructionN/A | Answer | Answer | |
To recognize revenues and expenses |
b. Prepare the 2020 journal entry to record profit or loss assuming revenue is recognized at a point in time. Note: If a journal entry (or a line of the journal entry) isn't required for the transaction, select "N/A" as the account names and leave the Dr. and Cr. answers blank (zero).
Account | Debit | Credit | |
---|---|---|---|
b. | AnswerCashAccounts ReceivableConstruction in ProcessBillings on ContractsLoss from Long Term ContractsRevenue from Long Term ContractsCost of ConstructionN/A | Answer | Answer |
AnswerCashAccounts ReceivableConstruction in ProcessBillings on ContractsLoss from Long Term ContractsRevenue from Long Term ContractsCost of ConstructionN/A | Answer | Answer | |
To recognize revenues and expenses |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started