On January 1, 2020, Red Sox Construction Ltd. started a construction project for $ 4,500,000. Relevant data for 2020 and 2021 are as follows: 2020
On January 1, 2020, Red Sox Construction Ltd. started a construction project for $ 4,500,000. Relevant data for 2020 and 2021 are as follows:
2020 2021
Current year construction costs $ 3,300,000 $ 620,000
Estimated remaining costs to complete 600,000 -0-
Current year billings 3,100,000 1,400,000
Current year collections 3,000,000 1,050,000
Instructions
Calculate the following amounts using the percentage of completion method. Please round all your answers to the nearest dollar:
- The amount of revenue recognized using the percentage completion method for 2020 and 2021. (3 marks)
- The amount of gross profit for 2020 and 2021. (4 marks)
- The year-end balance of Construction Contract Asset (Liability) for 2020 and 2021. (3 marks)
- The year-end balance of Accounts Receivable for 2020 and 2021. (2 marks)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started