On January 1, Miller Construction Company contracted to build a baseball stadium for the city of St. Denise for $24,000,000. The following transactions and estimates
On January 1, Miller Construction Company contracted to build a baseball stadium for the city of St. Denise for $24,000,000. The following transactions and estimates relate to this contract.
Construction costs incurred during the year | $3,960,000 |
Progress billings | $3,460,000 |
Cash collections | $2,960,000 |
Estimated costs to complete | $18,040,000 |
Required
1. The company accounts for revenue over time. Compute the percent complete at the end of the first year. Answer
%
2. Prepare the journal entries to record (a) costs incurred, (b) progress billings, (c) collections, and (d) any revenue or expense recognition.
Ref. | Account Name | Dr. | Cr. |
---|---|---|---|
a. | Accounts ReceivableBillings on ContractsCashConstruction in ProcessCost of ConstructionCost of Goods SoldDeferred RevenueRevenues from Long-Term ContractsSales RevenueN/ADebitN/ACredit | Answer
| |
Accounts ReceivableBillings on ContractsCashConstruction in ProcessCost of ConstructionCost of Goods SoldDeferred RevenueRevenues from Long-Term ContractsSales RevenueN/ADebitN/ACredit | Answer
| ||
To record constructions costs incurred | |||
b. | Accounts ReceivableBillings on ContractsCashConstruction in ProcessCost of ConstructionCost of Goods SoldDeferred RevenueRevenues from Long-Term ContractsSales RevenueN/ADebitN/ACredit | Answer
| |
Accounts ReceivableBillings on ContractsCashConstruction in ProcessCost of ConstructionCost of Goods SoldDeferred RevenueRevenues from Long-Term ContractsSales RevenueN/ADebitN/ACredit | Answer
| ||
To record progress billings | |||
c. | Accounts ReceivableBillings on ContractsCashConstruction in ProcessCost of ConstructionCost of Goods SoldDeferred RevenueRevenues from Long-Term ContractsSales RevenueN/ADebitN/ACredit | Answer
| |
Accounts ReceivableBillings on ContractsCashConstruction in ProcessCost of ConstructionCost of Goods SoldDeferred RevenueRevenues from Long-Term ContractsSales RevenueN/ADebitN/ACredit | Answer
| ||
To record collections | |||
d. | Accounts ReceivableBillings on ContractsCashConstruction in ProcessCost of ConstructionCost of Goods SoldDeferred RevenueRevenues from Long-Term ContractsSales RevenueN/ADebitN/ACredit | Answer
| |
Accounts ReceivableBillings on ContractsCashConstruction in ProcessCost of ConstructionCost of Goods SoldDeferred RevenueRevenues from Long-Term ContractsSales RevenueN/ADebitN/ACredit | Answer
| ||
Accounts ReceivableBillings on ContractsCashConstruction in ProcessCost of ConstructionCost of Goods SoldDeferred RevenueRevenues from Long-Term ContractsSales RevenueN/ADebitN/ACredit | Answer
| ||
To recognize revenues and expenses |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started