On January 1 , Miller Construction Company contracted to builed a parking lot for the city of St . Louis for $ 1 , 5
On January Miller Construction Company contracted to builed a parking lot for the city of StLouis for $ The following transactions and estimates relate to this contract.
The company accounts for revenue over time. Compute the percent complete at the end of the first year.
Prepare the journal entries to record a costs incurred, b progress billings, c collections, and d any revenue or expense recognition.