On January 1 st 2013 Hinkson Ltd entered into a contract with Seepersad Co to erect a building for a total contract price of $1,500,000.00.

On January 1st 2013 Hinkson Ltd entered into a contract with Seepersad Co to erect a building for a total contract price of $1,500,000.00. The following details are provided:

At Dec 31, 2013

At Dec 31, 2014

At Dec 31, 2015

Contract cost incurred to date

3500,000

730,000

945,000

Est. Cost to complete contract

1,050,000

730,000

405,000

Billings to Seepersad during year

300,000

400,000

300,000

a) Using the percentage of completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended Dec 31 2013, Dec 31 2014, Dec 31 2015.

b) Using the cost recovery method, compute the profit or loss to be recognized as a result of this contract for the years ended Dec 31 2013, Dec 31 2014, Dec 31 2015.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing And Systems Exam Questions And Explanations

Authors: Irvin N. Gleim

10th Edition

158194246X, 978-1581942460

More Books

Students also viewed these Accounting questions

Question

Socialize infrequently with colleagues outside of work

Answered: 1 week ago