On July 1, 2020, Cheyenne Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,910,000. On

On July 1, 2020, Cheyenne Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,910,000. On July 1, Cheyenne estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020, 2021, and 2022.

At 12/31/20 At 12/31/21 At 12/31/22
Contract costs incurred to date $285,000 $1,232,200 $2,114,200
Estimated costs to complete the contract 1,215,000 787,800 -0-
Billings to Gumbel 290,000 1,100,000 1,850,000

(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

To compute the profit or loss to be recognized for the years ended December 31 2020 2021 and 2022 using the percentageofcompletion method we need to p... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting

Authors: Jonathan E. Duchac, James M. Reeve, Carl S. Warren

23rd Edition

978-0324662962

More Books

Students also viewed these Accounting questions