On June 1 2 th , Delta Corporation was awarded a $ 1 6 0 K contract for Project X . The contract consisted of
On June th Delta Corporation was awarded a $K contract for Project X The contract consisted of $K for labor and materials with the remaining $K as projected profit. The project started on July rd The Network Logic and Project Planning Budget as developed by the project manager was as follows:
Network Logic:
Starting Node
Ending Node
Duration Weeks
A
B
A
C
A
D
B
C
B
E
C
F
D
F
E
F
F
G
Project Planning Budget:
P Project Planning Budget.png
On August th weeks into project Deltas CEO received the following status report:
Activity
Complete
Actual Cost Ks
Time remaining Weeks
AB
$
AC
$
AD
$
BC
$
BE
$
The CEO could not identify the real status of the project from this report, even after comparing the report the Project Planning Budget. As such, you have been asked to prepare a better status report using the format below to depict the true status of the project including how much profit the project is expected to yield now after week
Status Report Format:
Activity
Percent Complete
BCWS
BCWP
BCWP using Rule
ACWP
CV
SV
CV using Rule
SV using Rule
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started