Question
On June 15, 2016, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $220 million. The expected
On June 15, 2016, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $220 million. The expected completion date is April 1, 2018, just in time for the 2018 baseball season. Costs incurred and estimated costs to complete at the year end for the life of the contract are as follows (in millions):
2016 | 2017 | 2018 | |
Costs incurred during the year | $40 | $80 | $50 |
Estimated costs to complte as of December 31 | $120 | $60 | ----- |
Required:
1) How much revenue and gross profit will sanderson report in its 2016, 2017 and 2018 income statements related to this contract assuming Sanderson recognizes revenue over time according to percentage of completion?
2) How much revenue and gross profit will Sanderson report in its 2016, 2017 and 2018 income statements related to this contract assuming the project does not qualify for revenue recognition over time?
3) Suppose the estimated costs to complete at the end of 2017 are $80 million instead of $60 million. Determine the amount of revenue and gross profit or loss to be recognized in 2017 assuming Sanderson recognizes revenue over time according to percentage of completion.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started