On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $370 million. The expected

On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $370 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions):

2021 2022 2023
Costs incurred during the year $ 70 $ 110 $ 80
Estimated costs to complete as of December 31 180 60

Required: 1. Compute the revenue and gross profit will Sanderson report in its 2021, 2022, and 2023 income statements related to this contract assuming Sanderson recognizes revenue over time according to percentage of completion. 2. Compute the revenue and gross profit will Sanderson report in its 2021, 2022, and 2023 income statements related to this contract assuming this project does not qualify for revenue recognition over time. 3. Suppose the estimated costs to complete at the end of 2022 are $180 million instead of $60 million. Compute the amount of revenue and gross profit or loss to be recognized in 2022 assuming Sanderson recognizes revenue over time according to percentage of completion.

Percentages of completion
Choose numerator Choose denominator = % complete to date
2021 $70 $250 = 28.00%
2022 $180 $250 = 72.00%
2023 $260 $260 100.00%
2021
To date Recognized in prior years Recognized in 2021
Construction revenue $0
Construction expense $0
Gross profit (loss) $0
2022
To date Recognized in prior years Recognized in 2022
Construction revenue $0
Construction expense $0
Gross profit (loss) $0
2023
To date Recognized in prior years Recognized in 2023
Construction revenue $0
Construction expense $0
Gross profit (loss) $0

image text in transcribed

image text in transcribed

Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Compute the revenue and gross profit will Sanderson report in its 2021, 2022, and 2023 income statements related to this contract assuming this project does not qualify for revenue recognition over time. (Enter your answers in millions. Loss amounts should be indicated with a minus sign.) Year 2021 2022 2023 Revenue recognized million million million Gross Profit (Loss) recognized million million million Required 1 Required 2 Required 3 Suppose the estimated costs to complete at the end of 2022 are $180 million instead of $60 million. Compute the amount of revenue and gross profit or loss to be recognized in 2022 using the percentage of completion method. (Enter your answers in millions. Use percentages as calculated and rounded in the table below to arrive at your final answer.) Percentages of completion Choose numerator Choose denominator % complete to date 2022 0 2022 Recognized in prior Years To date Recognized in 2022 $ $ Construction revenue Construction expense Gross profit (loss) $ $ 0 0 0

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management And Cost Accounting

Authors: Mike Tayles, Colin Drury

11th Edition

147377361X, 978-1473773615

More Books

Students also viewed these Accounting questions

Question

=+3. Who are the brand's competitors?

Answered: 1 week ago

Question

11.7 Discuss competency-based pay.

Answered: 1 week ago