Answered step by step
Verified Expert Solution
Question
1 Approved Answer
On June 15, 2024, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $230 million. The
On June 15, 2024, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $230 million. The expected completion date is April 1, 2026, just in time for the 2026 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year 2024 $ 25 Estimated costs to complete as of December 31 100 2025) $75 68 2026 $ 35 Required: 1. Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this contract, assuming Sanderson recognizes revenue over time according to percentage of completion. 2. Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this contract, assuming this project does not qualify for revenue recognition over time. 3. Suppose the estimated costs to complete at the end of 2025 are $100 million instead of $60 million. Compute the amount of revenue and gross profit or loss to be recognized in 2025, assuming Sanderson recognizes revenue over time according to percentage of completion. Complete this question by entering your answers in the tabs below. Required 1 Required 2 25 points Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this contract, assuming Sanderson recognizes revenue over time according to percentage of completion. Note: Enter your answer in millions (i.e., $4,000,000 should be entered as $4). Loss amounts should be indicated with a minus sign. Use percentages as calculated and rounded in the table below to arrive at your final answer. Percentages of completion Show less A 2024 eBook 2025 . 2026 Him Prim D 2024 To date Recognized in prior years Recognized in 2024 Construction revenue Construction expense Gross profit (loss) Construction revenue i Construction expense Gross profit (loss) Construction revenue Construction expense Gross profit pose) 2025 To date Recognized in prior years Recognized in 2025 2026 To date Recognized in prior years) Recognized in 2026 Required 1 Required 2 > Required 1 Required 2 References Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this contract, assuming this project does not qualify for revenue recognition over time. Note: Enter your answer in millions (i.e., $4,000,000 should be entered as $4). Loss amounts should be indicated with a minus sign. Leave no cells blank. Year Revenue recognized Gross Profit (Loss) recognized 2024 million million 2025 2026 million million million million Required Show less A
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started