Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

On June 15, 2024, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $230 million. The expected

On June 15, 2024, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $230 million. The expected completion date is April 1, 2026, just in time for the 2026 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 Required: 2024 $ 25 100 2025 $ 75 60 2026 $ 35 1. Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this contract, assuming Sanderson recognizes revenue over time according to percentage of completion. 2. Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this contract, assuming this project does not qualify for revenue recognition over time. 3. Suppose the estimated costs to complete at the end of 2025 are $100 million instead of $60 million. Compute the amount of revenue and gross profit or loss to be recognized in 2025, assuming Sanderson recognizes revenue over time according to percentage of completion. Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this contract, assuming Sanderson recognizes revenue over time according to percentage of completion. Note: Enter your answer in millions (i.e., $4,000,000 should be entered as $4). Loss amounts should be indicated with a minus sign. Use percentages as calculated and rounded in the table below to arrive at your final answer. 2024 2025 2026 Percentages of completion = = 2024 To date Recognized in prior years Recognized in 2024 Construction revenue Construction expense Gross profit (loss) 2025 To date Recognized in prior years Recognized in 2025 Construction revenue Construction expense Gross profit (loss) Construction revenue Construction expense Gross profit (loss) 2026 To date Recognized in prior years Recognized in 2026 Show less On June 15, 2024, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $230 million. The expected completion date is April 1, 2026, just in time for the 2026 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year 2024 $ 25 Estimated costs to complete as of December 31 Required: 100 2025 $ 75 60 2026 $ 35 1. Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this contract, assuming Sanderson recognizes revenue over time according to percentage of completion. 2. Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this contract, assuming this project does not qualify for revenue recognition over time. 3. Suppose the estimated costs to complete at the end of 2025 are $100 million instead of $60 million. Compute the amount of revenue and gross profit or loss to be recognized in 2025, assuming Sanderson recognizes revenue over time according to percentage of completion. Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this contract, assuming this project does not qualify for revenue recognition over time. Note: Enter your answer in millions (i.e., $4,000,000 should be entered as $4). Loss amounts should be indicated with a minus sign. Leave no cells blank. Year Revenue recognized Gross Profit (Loss) recognized 2024 million million 2025 million million 2026 million million Show less On June 15, 2024, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $230 million. The expected completion date is April 1, 2026, just in time for the 2026 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 Required: 2024 $ 25 100 2025 $ 75 2026 $ 35 60 1. Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this contract, assuming Sanderson recognizes revenue over time according to percentage of completion. 2. Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this contract, assuming this project does not qualify for revenue recognition over time. 3. Suppose the estimated costs to complete at the end of 2025 are $100 million instead of $60 million. Compute the amount of revenue and gross profit or loss to be recognized in 2025, assuming Sanderson recognizes revenue over time according to percentage of completion. Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Suppose the estimated costs to complete at the end of 2025 are $100 million instead of $60 million. Compute the amount of revenue and gross profit or loss to be recognized in 2025, assuming Sanderson recognizes revenue over time according to percentage of completion. Note: Enter your answer in millions (i.e., $4,000,000 should be entered as $4). Use percentages as calculated and rounded in the table below to arrive at your final answer. Loss amounts should be indicated with a minus sign. 2025 Construction revenue Construction expense Gross profit (loss) Percentages of completion Choose numerator Choose denominator % complete to date = 2025 To date Recognized in prior Years Recognized in 2025 Show less

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions