Question

1 Approved Answer

On March 1, 2010, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The

On March 1, 2010, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The building was completed by October 31, 2012. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2010, 2011, and 2012 are given below:

image text in transcribed

(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2010, 2011, and 2012. (Ignore income taxes.)

(b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2010, 2011, and 2012. (Ignore incomes taxes.)

2012 $1,070,000 Costs incurred to date Estimated costs to complete Billings to date Collections to date 2010 $400,000 600,000 300,000 270,000 2011 $825,000 275,000 900,000 810,000 1,600,000 1,425,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Money Talks Explaining How Money Really Works

Authors: Nina Bandelj ,Frederick F. Wherry ,Viviana A. Zelizer

1st Edition

0691202893, 978-0691202891

More Books

Students also viewed these Finance questions