On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on land costing $800,000 (purchased from the contractor and included
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on land costing $800,000 (purchased from the contractor and included in the first payment). The construction began on the office building on March 1. The following expenditures were incurred for construction:
Date Expenditures
March 1, 2019 $ 1,200,000
May 1, 2019 1,680,000
August 1, 2019 3,000,000
September 30, 2019 4,800,000
The building was completed and ready for occupancy on September 30, 2019. To finance purchase of the land and construction of the building, $1,500,000 was borrowed on March 1, 2019 on a 9%, 3-year note payable. Other than the construction note, the only debt outstanding during 2019 was a $1,000,000, 12%, 6-year note payable dated January 1, 2019.
The interest cost to be capitalized during 2019 is
Select one:
a. $ 135,000
b. $ 195,000
c. $ 159,000
d. $ 183,000
Step by Step Solution
There are 3 Steps involved in it
Step: 1
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started