Question

1 Approved Answer

On March 1, 2020, Sheridan Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,330,000. The

On March 1, 2020, Sheridan Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,330,000. The building was completed by October 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below:

2020

2021

2022

Contract costs incurred during the year $2,662,800 $2,188,000 $2,389,200
Estimated costs to complete the contract at 12/31 3,677,200 2,389,200 0
Billings to Fabrik during the year 3,180,000 3,480,000 1,670,000

(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Intermediate Accounting

Authors: Donald E. Kieso, Jerry J. Weygandt, Terry D. Warfield

16th edition

1118742974, 978-1118743201, 1118743202, 978-1118742976

More Books

Students also viewed these Accounting questions