Question
on march 1 2021, Beldon corporation purchased land as a factory site for $64000. An old building on the property was demolished, and construction began
on march 1 2021, Beldon corporation purchased land as a factory site for $64000. An old building on the property was demolished, and construction began on a new building that was completed December 15,2021. Cost incurred are listed below:
demolition of old building: $6000
architect fees $16000
legal fees for title investigation $4000
property taxes (period beginning March 1,2021) $3400
construction cost $54000
interest on construction loan $7000
salvage materials from old building were sold for $2400
required:
determine the amounts that Beldon should capitalize as the cost of the land and the new building
Capitalized cost of land:
Total cost of land:
Capitalized cost of building:
Total cost of building:
Please show all work.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started