Answered step by step
Verified Expert Solution
Question
1 Approved Answer
On the start of the project 2 activities A&B start in parallel, on the finish of activity B activity D can start ,& on
On the start of the project 2 activities A&B start in parallel, on the finish of activity B activity D can start ,& on the finish of both the activities A&B activity C can start. When activity C finishes activity E can start & when both the activities i:e C&D finish activity F can start. On the finish of activity F, activities G, H & I start in parallel. When activity G finishes activity J starts. Activities J, H &I give output to activity K. Activity K & E give output to activity L which is the last activity of the project. Task A Optimistic 5 Pessimistic 10 Most Likely 8 B C 18 26 16 22 40 20 20 33 18 (i) (ii) (iv) D E 15 25 20 F 6 12 9 From the given logic and the data do the following:- G 7 12 10 H 3 5 4 I 10 18 15 For each task determine the expected task time and their variance. Draw the network diagram in AIB format. Determine ES and EF of each activity. Find the critical path of the project. J 2 6 4 K L 20 10 25 15 22 12 (20)
Step by Step Solution
★★★★★
3.36 Rating (162 Votes )
There are 3 Steps involved in it
Step: 1
we will use the PERT Program Evaluation and Review Technique method i To calculate the expected task ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started