On this AON diagram, if activity H is crashed by 3 days, what would be the new length of the project? A-9 C-3 ACEHI
On this AON diagram, if activity H is crashed by 3 days, what would be the new length of the project? A-9 C-3 ACEHI ACEGI ADEGI ADFGI ADEHI 26 26 24 30 36 25 D-5 E-4 F-2 H-8 G-6 1-2 13