One of Swifty Fireworks Company's activity cost pools is machine setups, with estimated overhead of $191000. Astro produces sparklers (70 setups) and lighters ( 30
One of Swifty Fireworks Company's activity cost pools is machine setups, with estimated overhead of $191000. Astro produces sparklers (70 setups) and lighters ( 30 setups). How much of the machine setup cost pool should be assigned to sparklers? $245571$133700$191000$57300