One of the project success criteria stated in the project charter is: The project must finish within budget. Which of the following is correct? This
One of the project success criteria stated in the project charter is: "The project must finish within budget." Which of the following is correct? This is a good success criteria it is very objective. This is a good success criteria, a good project is always within budget. This is a bad success criteria, budget cannot be used as a criteria This is a bad success criteria it is too general and applies to any project