One of the team members is new to Agile and seek to understand what is meant by the release backlog. When applying holistic scope planning
One of the team members is new to Agile and seek to understand what is meant by the release backlog. When applying holistic scope planning to agile methods, which statement BEST describes release backlog? a The work that is planned to be completed in the current release bThe work that is committed to be completed in the current sprint The work that is planned to be completed in the next iteration The work that is committed to be completed in the next iteration