Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Optimistic Most Probable Pessimistic Activity Time Time Time A 4 5 6 B 2 . 5 3 3 . 5 C 6 7 8 D

Optimistic Most Probable Pessimistic
Activity Time Time Time
A 456
B 2.533.5
C 678
D 55.59
E 678
F 135
G 81012
Suppose that the critical path is A-C-E-F-G. Use Appendix A to answer the questions. Do not round intermediate calculations. Round your answers to three decimal places.
What is the probability that the project will be completed within 33 weeks?
What is the probability that the project will be completed within 30 weeks?
What is the probability that the project will be completed in more than 31 weeks?
What is the probability that the project will be completed in 32 weeks?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Perioperative Pain Management For General And Plastic Surgery

Authors: Deepak Narayan, Alan D Kaye, Nalini Vadivelu

1st Edition

0190457007, 978-0190457006

More Books

Students also viewed these General Management questions

Question

Describe the options and trends in management education

Answered: 1 week ago