Question
1 Approved Answer
Order Point = DDLT +SS DDLT= Demand During Lead time SS= Safety Stock Safety stock is one standard deviation and one standard deviation = 200
Order Point = DDLT +SS
DDLT= Demand During Lead time
SS= Safety Stock
Safety stock is one standard deviation and one standard deviation = 200 units.
Calculate Order Point if DDLT is 1000 units. Also calculate order pint when safety stock is 2 standard deviations.
What is the safety stock if Order point is 3000 and demand during demand during lead time is 2000 units?