Question

1 Approved Answer

Order Point = DDLT +SS DDLT= Demand During Lead time SS= Safety Stock Safety stock is one standard deviation and one standard deviation = 200

Order Point = DDLT +SS

DDLT= Demand During Lead time

SS= Safety Stock

Safety stock is one standard deviation and one standard deviation = 200 units.

Calculate Order Point if DDLT is 1000 units. Also calculate order pint when safety stock is 2 standard deviations.

What is the safety stock if Order point is 3000 and demand during demand during lead time is 2000 units?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Managerial Approach

Authors: Jack R. Meredith, Samuel J. Mantel Jr.

8th edition

470533021, 978-0470533024

More Books

Students also viewed these General Management questions

Question

Show the linkage between strategic planning and planning

Answered: 1 week ago