Question
Order Taking Run Time:1 minute per item (or 3 minutes per order) Capacity: 1 item per minute*60=60 items per order Pre-Treatment Run Time: 60 minutes/56.8
Order Taking
Run Time:1 minute per item (or 3 minutes per order)
Capacity: 1 item per minute*60=60 items per order
Pre-Treatment
Run Time: 60 minutes/56.8 items per hour=1.06 minutes per item
Capacity: 90 items in 90 minutes with 5 minutes of setup, (90/95 minutes) x 60 minutes/hour = 56.8 items per hour
Dry Cleaning
Run Time: 5 minutes set up time and 55 minutes run-time per 90 item batch
(60/60=1 batch)
Capacity: 90 items per hour. Capacity can be increased if consecutive loads are of the same color
Pressing
Run Time: The pressure can process an item in 2.5 minutes: 60 minutes per hour/2.5 minutes per item=24 items per hour
Capacity: 60minutes/2.5minutes per item = 24 x 2= 48 items per hour between the two pressers.
Packing
Run Time: 0.5 minutes per item or 2 items per minute
Capacity: 2 items per minute x 60 minutes = 120 items per hour
Customer Pickup & Payment
Run Time: 1 minute per item
Suppose 200 customers drop off laundry over a typical 12-hour day.What is the utilization of each of the different stages of the dry-cleaning process?Will there be a problem?The different stages are: order taking, pre-treatment, dry-cleaning, pressing, packing, and pickup & payment.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started