Oriole Construction Company began work on a $403,500 construction contract in 2020. During 2020, Oriole incurred costs of $263,000, billed its customer for $209,500, and

Oriole Construction Company began work on a $403,500 construction contract in 2020. During 2020, Oriole incurred costs of $263,000, billed its customer for $209,500, and collected $172,000. At December 31, 2020, the estimated additional costs to complete the project total $160,510. Prepare Orioles journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required, select "No entry" for the account titles and enter 0 for the amounts. Round answers to 0 decimal places, e.g. 5,275.)

No.

Account Titles and Explanation

Debit

Credit

(a)

enter an account title to record the transaction using the percentage-of-completion method

enter a debit amount

enter a credit amount

enter an account title to record the transaction using the percentage-of-completion method

enter a debit amount

enter a credit amount

enter an account title to record the transaction using the percentage-of-completion method

enter a debit amount

enter a credit amount

(b)

enter an account title to record the transaction using the completed-contract method

enter a debit amount

enter a credit amount

enter an account title to record the transaction using the completed-contract method

enter a debit amount

enter a credit amount

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Audit Planning Conduct And Closure Of Issues For Successful Resolution

Authors: Bincy Abraham, Imran Chaki, Naisarg Pujara

1st Edition

6200484961, 978-6200484963

More Books

Students also viewed these Accounting questions