Question
Oriole Construction Company had a contract starting April 2021, to construct a $24300000 building that is expected to be completed in September 2023, at an
Oriole Construction Company had a contract starting April 2021, to construct a $24300000 building that is expected to be completed in September 2023, at an estimated cost of $22300000. At the end of 2021, the costs to date were $10927000 and the estimated total costs to complete had not changed. The progress billings during 2021 were $5100000 and the cash collected during 2021 was 3230000. Oriole uses the percentage-of-completion method. For the year ended December 31, 2021, Oriole would recognize gross profit on the building of:
a. $899342.
b. $980000.
c. $0.
d. $11373000.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started