Oriole, Inc., has collected the following information on its cost of electricity: Machine Hours Total Electricity Costs January 500 $240 February 540 $300 March 370
Oriole, Inc., has collected the following information on its cost of electricity:
Machine Hours | Total Electricity Costs | ||||
January | 500 | $240 | |||
February | 540 | $300 | |||
March | 370 | $210 | |||
April | 440 | $220 | |||
May | 680 | $290 | |||
June | 730 | $330 | |||
July | 330 | $180 | |||
August | 530 | $260 | |||
September | 230 | $118 | |||
October | 740 | $340 | |||
November | 860 | $370 | |||
December | 600 | $340 |
Using the high-low method, compute the variable cost of electricity per machine hour. (Round unit cost to 2 decimal places, e.g. 52.75.)
Variable cost | $ per machine hour |
Compute the total fixed cost of electricity. (Round answer to 2 decimal places, e.g. 52.75.)
Fixed cost | $ |
Represent the electricity cost function in equation form. (Round answers to 2 decimal places, e.g. 52.75.)
Total cost = | $ MH | + | $ |
What is the expected electricity cost when 740 machine hours are used? (Round answer to 2 decimal places, e.g. 52.75.)
Total cost | $ |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started