Ornamental Sculptures Mfg. manufactures garden sculptures. Each sculpture requires 9 pounds of direct materials at a cost of $2 per pound and 0.4 direct labor

image text in transcribed
image text in transcribed
image text in transcribed
Ornamental Sculptures Mfg. manufactures garden sculptures. Each sculpture requires 9 pounds of direct materials at a cost of $2 per pound and 0.4 direct labor hours at a rate of $19 per hour. Variable manufacturing overhead is charged at a rate of $3 per direct labor hour. Fixed manufacturing overhead is $3,200 per month. The company's policy is to maintain direct materials inventory equal to 30% of the next month's materials requirement. At the end of February the company had 5,680 pounds of direct materials in inventory. The company's production budget reports the following. Production Budget Units to be produced March 3,700 April 5,400 May 5,600 (1) Prepare direct materials budgets for March and April. (2) Prepare direct labor budgets for March and April (3) Prepare factory overhead budgets for March and April. Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Prepare direct materials budgets for March and April April ORNAMENTAL SCULPTURES MFG. Direct Materials Budget For the Months of March and April March Budgeted production (units) Materials requirements per unit (lbs.) Materials needed for production (lbs.) 0 Budgeted ending inventory (lbs.) Total materials requirements (lbs.) 0 Budgeted beginning inventory (lbs) Materials to be purchased (lbs) 0 Direct material cost per lb. Total budgeted direct materials 0 0 0 0 $ $ 0 Required 1 Required 2 > Production Budget Units to be produced March 3,700 April 5,400 May 5,600 5 (1) Prepare direct materials budgets for March and April. (2) Prepare direct labor budgets for March and April. (3) Prepare factory overhead budgets for March and April. Complete this question by entering your answers in the tabs belov Required 1 Requked 2 Required 3 Prepare direct labor budgets for March and April. (Round "DL hours required April ORNAMENTAL SCULPTURES MFG. Direct Labor Budget For the Months of March and April March Budgeted production (units) DL hours required per unit Total direct labor hours needed 0 Direct labor rate per hour Total budgeted direct labor $ 0 $ 0 0 Produ Units to be produced 3,700 5,400 5,600 (1) Prepare direct materials budgets for March and April. (2) Prepare direct labor budgets for March and April. (3) Prepare factory overhead budgets for March and April. Complete this question by entering your answers in the tabs Required 1 Required 2 Required 3 Prepare factory overhead budgets for March and April. ORNAMENTAL SCULPTURES MFG. Factory Overhead Budget For the Months of March and April March April Total direct labor hours needed VOH rate per DL hour Budgeted variable overhead $ 0 $ Budgeted fixed overhead Total budgeted factory overhead $ 0 $

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Audit Of The Federal Bureau Of Investigation Annual Financial Statements Fiscal Year 2015

Authors: Office Of The Inspector G Eneral, U.S. Department Of Justice

1st Edition

1530341264, 978-1530341269

More Books

Students also viewed these Accounting questions