Question
ou are estimating your activity durations using Bottom-Up estimating. What does this mean? Select one: a. You are estimating the number of resources required for
ou are estimating your activity durations using Bottom-Up estimating. What does this mean?
Select one:
a.
You are estimating the number of resources required for each work package to increase the probability of being able to meet the estimated durations
b.
You are estimating the cost of each activity at the lowest possible level of detail
c.
You are performing decomposition on the deliverables to form Work Packages
d.
You are using detailed activity lists to assign individual activity durations so that they can be aggregated, while considering dependencies among activities
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started